Euro Manganese Provides Chvaletice Manganese Project and Corporate Update - Yahoo Finance

Highlights:

  • Assembly of the Project’s Demonstration Plant (DP) at a facility in China is proceeding as planned, with cold commissioning of the plant modules set to begin this month.

  • The construction permit was issued for upgrading and adapting buildings at the Chvaletice Manganese Project site that will house the DP. Site preparations for receiving and installing the DP modules are underway.

  • Delivery of the DP modules to the Chvaletice site is expected early in the New Year, with hot commissioning and start-up targeted for the second quarter of 2022.

  • The Project’s pilot plant was restarted during October to produce small samples of high-purity manganese products for prospective customers. Sample deliveries are expected in the first quarter of 2022.

  • Work on the Project’s definitive feasibility study is ongoing, with all verification and testing work complete and good progress being made on engineering studies. To date, the study is tracking on schedule and on budget, with approximately 60% of physical progress complete as at the end of September, 2021.

  • Euro Manganese has engaged consulting firms Minviro Ltd. and RCS Global Group to conduct a joint Life Cycle Assessment of the Chvaletice Manganese Project as part of the Company’s commitment to environmental excellence.

  • In September, Euro Manganese received its ISO 27001 certification for Information Security Management Systems (ISMS), recognized globally as proof that the Company’s ISMS is in line with the information...



Read Full Story: https://finance.yahoo.com/news/euro-manganese-provides-chvaletice-manganese-223000823.html

Your content is great. However, if any of the content contained herein violates any rights of yours, including those of copyright, please contact us immediately by e-mail at media[@]kissrpr.com.